近日,徐淮阜高速淮北段上(shang)跨臥龍湖煤(mei)礦鐵路(lu)專用線立交工程梁板全(quan)部架設完(wan)成,為后續(xu)橋面(mian)系及(ji)附(fu)屬工程施(shi)工創造了有利(li)條件。
徐(xu)淮(huai)阜高速公路(lu)淮(huai)北段項目共有2座涉鐵(tie)橋(qiao)梁(liang),分別為上跨臥龍湖煤礦鐵(tie)路(lu)專用(yong)(yong)線立(li)交工(gong)程和上跨劉橋(qiao)煤礦鐵(tie)路(lu)專用(yong)(yong)線立(li)交工(gong)程。其(qi)中,上跨臥龍湖煤礦鐵(tie)路(lu)專用(yong)(yong)線立(li)交工(gong)程全長621米,全橋(qiao)預制箱梁(liang)共計206片(pian)。
進入二季度以來,項(xiang)(xiang)(xiang)目(mu)方統籌抓(zhua)好資源(yuan)調(diao)配和施(shi)工(gong)(gong)(gong)組織,聚力克(ke)難、集智攻關,搶抓(zhua)項(xiang)(xiang)(xiang)目(mu)建設“黃金期”,全力疏“通”多項(xiang)(xiang)(xiang)關鍵節點(dian),吹響“奮戰六月(yue)份,沖刺‘雙過半(ban)’”沖鋒號。施(shi)工(gong)(gong)(gong)過程中(zhong),為確保列車運行不受影響,項(xiang)(xiang)(xiang)目(mu)方提前(qian)(qian)完成跨鐵施(shi)工(gong)(gong)(gong)手(shou)續(xu)報批,為架梁(liang)施(shi)工(gong)(gong)(gong)爭取(qu)“天窗(chuang)點(dian)”,并積極(ji)克(ke)服安(an)全風(feng)險高等不利(li)因素,詳細制定架梁(liang)施(shi)工(gong)(gong)(gong)專(zhuan)項(xiang)(xiang)(xiang)方案,精準把控(kong)施(shi)工(gong)(gong)(gong)關鍵工(gong)(gong)(gong)序,提前(qian)(qian)1個月(yue)完成了全部(bu)梁(liang)板架設節點(dian)計劃。